Sr. No. | Name of Service | Average Fee |
Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act |
Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval | Minimum Time To Grant Approval | Maximum Time To Grant Approval | Rating & Feedback |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Registration / Renewal of principal employer's establishment under provision of The Contracts Labour (Regulation and Abolition) Act, 1970 | 20 | ||||||||||
2 | Registration / Renewal under "The Building and Other Construction Workers (Regulation of Employment Conditions of Service Act), 1996" | 20 | ||||||||||
3 | Registration under "Shops & Establishment Act" | 15 | ||||||||||
4 | Registration Certificate of "Establishment Inter State Migrant Workmen (RE&CS) Act, 1979 (License of Contractor Establishment)" | 20 | ||||||||||
5 | Single Annual Return form | 20 | ||||||||||
6 | Renewal under "Shops and Establishment Act" | 20 | ||||||||||
7 | License for Contractors under provision of The Contracts Labour (R & A) Act,1970 | 20 | ||||||||||
8 | Renewal Certificate of "Establishment Inter State Migrant Workmen (RE&CS) Act, 1979 (License of Contractor Establishment)" | 20 | ||||||||||
9 | Renewal License for Contractors under provision of The Contracts Labour (R & A) Act,1970 | 20 |
Sr. No. | Name of Service | Average Fee |
Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act |
Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval | Minimum Time To Grant Approval | Maximum Time To Grant Approval | Fee Incurred to Grant Approval / Certificate | Rating & Feedback |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Incentives under Investment Promotion Scheme - 2015 for MSME | 30 | Not Applicable | ||||||||||
2 | Incentives under Investment Promotion Scheme - 2015 for Textile Sector | 30 | Not Applicable | ||||||||||
3 | NOC of Lease | 30 | Not Applicable | ||||||||||
4 | Sale/Transfer of Lease | 30 | Not Applicable | ||||||||||
5 | Subletting | 30 | Not Applicable | ||||||||||
6 | Sublessee | 30 | Not Applicable | ||||||||||
7 | Seller Of Lease | 30 | Not Applicable | ||||||||||
8 | Allotment of land in Industrial Area | 30 | Not Applicable | ||||||||||
9 | Investment Promotion Scheme : 2022 to 2027 | 30 | Not Applicable | ||||||||||
10 | licence of Lubricating Oil or Grease | 30 | Not Applicable |
Sr. No. | Name of Service | Average Fee |
Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act |
Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval | Minimum Time To Grant Approval | Maximum Time To Grant Approval | Rating & Feedback |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Registration of license under The Factories Act, 1948 | 20 | ||||||||||
2 | Approval of plan and permission to construct/extend/or take into use any building as a factory under the Factories Act, 1948 | 15 | ||||||||||
3 | Registration of Boilers under The Boilers Act, 1923 | 30 | ||||||||||
4 | Registration / Renewal of Boilers Manufactures under The Boilers Act, 1923 | 15 | ||||||||||
5 | Renewal of license under The Factories Act, 1948 | 60 | ||||||||||
6 | Renewal of Boilers under The Boilers Act, 1923 | 15 |
Sr. No. | Name of Service | Average Fee |
Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act |
Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval | Minimum Time To Grant Approval | Maximum Time To Grant Approval |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Mobile Tower Approval | - | 7 Days | - | - | - | - | 5 Day(s) | 6 Day(s) | - | - |
2 | Trade Licenses | 7 Days | 587 | 587 | 183 | 404 | 6 Day(s) | 7 Day(s) | - | - |
Sr. No. | Name of Service | Average Fee |
Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act |
Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval | Minimum Time To Grant Approval | Maximum Time To Grant Approval | Rating & Feedback |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Application for State Cinema Regulations | 45 | ||||||||||
2 | Application for Permission from District Collector for Movie Shooting (Integrated with Police & Traffic / State Protected Monument / Municipal Councils) | 5 | ||||||||||
3 | Change In Land Use ( N.A.) | 90 | ||||||||||
4 | Society Registration | 30 |
Sr. No. | Name of Service | Average Fee |
Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act |
Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval | Minimum Time To Grant Approval | Maximum Time To Grant Approval | Rating & Feedback |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Registration under "Weights & Measure" | 30 | ||||||||||
2 | Registration under "License for Repairer" | 30 | ||||||||||
3 | Registration under "License for Dealer" | 30 | ||||||||||
4 | Registration under "License for Manufacturer" | 30 | ||||||||||
5 | Renewal under "License for Repairer" | 30 | ||||||||||
6 | Renewal under "License for Dealer" | 30 | ||||||||||
7 | Renewal under "License for Manufacturer" | 30 | ||||||||||
8 | Application for Verification / Re-verification / Stamping of Weights & Measures | 7 | ||||||||||
9 | Reporting/Informing/Intimation to Legal Metrology Office | 30 | ||||||||||
10 | Online Registers/Periodical Return Form | 30 |
Sr. No. | Name of Service | Average Fee |
Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act |
Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval | Minimum Time To Grant Approval | Maximum Time To Grant Approval |
---|---|---|---|---|---|---|---|---|---|---|---|
1 |
Issue of New Electricity Connection
a) Temporary connection |
- | 15 Days | 10 | 10 | 6 | 4 | 4 | 3 Application in 5 Days |
- | - |
2 |
Issue of New Electricity Connection
b) LT connection |
- | 45 Days | 122 | 122 | 102 | 20 | 8 | 12 Application in 11 Days |
- | - |
3 |
Issue of New Electricity Connection
c) HT connection |
- | 45 Days | 13 | 13 | 13 | 0 | 4 | 2 Application in 8 Days |
- | - |
4 | Approval for DG set installation (Registration and Renewal) | - | 15 Days | 16 | 16 | 16 | 0 | 10 | 3 Application in 15 Days | - | - |
Sr. No. | Name of Service | Average Fee |
Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act |
Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval | Minimum Time To Grant Approval | Maximum Time To Grant Approval | Rating & Feedback |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | New Water Connection or Certificate of Non-Availability of Water | 7 | 5 Days | 2 Application in 7 Days |
Sr. No. | Name of Service | Average Fee |
Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act |
Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval | Minimum Time To Grant Approval | Maximum Time To Grant Approval | Rating & Feedback |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Hotel & Home Stay /Bed & Breakfast Registration Form | 21 | ||||||||||
2 | Travel Agency Registration Form | 21 | ||||||||||
3 | Hotel & Home Stay / Bed & Breakfast Registration Renewal Form | 21 | ||||||||||
4 | Travel Agency Form - Renewal | 21 | ||||||||||
5 | Tourism Event - Performance | 21 |
Sr. No. | Name of Service | Average Fee |
Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act |
Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval | Minimum Time To Grant Approval | Maximum Time To Grant Approval | Rating & Feedback |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Partnership Firms Registration | 15 | ||||||||||
2 | Nil Certificate for Encumbrance | 30 | ||||||||||
3 | Property Registration | Same Day | Same Day |
Sr. No. | Name of Service | Average Fee |
Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act |
Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval | Minimum Time To Grant Approval | Maximum Time To Grant Approval | Rating & Feedback |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Construction Permission (Include Storage of Construction Material) | 21 | ||||||||||
2 | Application for Inspection at Plinth level | 15 | ||||||||||
3 | Occupancy Certificate / Part Occupancy Certificate | 30 | ||||||||||
4 | Site Elevation | 10 | ||||||||||
5 | Zone Information | 7 |
Sr. No. | Name of Service | Average Fee |
Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act |
Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval | Minimum Time To Grant Approval | Maximum Time To Grant Approval |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Label Registration/Brand Registration | - | 10 Days | 0 | 0 | 0 | 0 | - | - | - | - |
2 | Export Permit (spirit) by Distilleries/Industries | - | 3 Days | 0 | 0 | 0 | 0 | - | - | - | - |
3 | Export Permits(IMFL/CL/Beer/FL) by Distilleries/Brewery | - | 3 Days | 0 | 0 | 0 | 0 | - | - | - | - |
4 | Import Permit (spirit) by Distilleries/Industries | - | 3 Days | 0 | 0 | 0 | 0 | - | - | - | - |
5 | Import Permits(IMFL/CL/Beer/FL) by Wholesalers | - | 3 Days | 0 | 0 | 0 | 0 | - | - | - | - |
6 | Local Sale/Transport Permits(Spirit) by Distilleries/Industries) | - | 1 Days | 0 | 0 | 0 | 0 | - | - | - | - |
7 | Local Sale Permits(IMFL/CL/Beer/FL) by Distilleries/Brewery/Wholesalers | - | 1 Days | 0 | 0 | 0 | 0 | - | - | - | - |
8 | Occasional License | - | 7 Days | 0 | 0 | 0 | 0 | - | - | - | - |
9 | Renewal of Licenses(Distilleries/Brewery/Wholesalers/Retailers/Hotels) | - | 30 Days | 0 | 0 | 0 | 0 | - | - | - | - |
Sr. No. | Name of Service | Average Fee |
Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act |
Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval | Minimum Time To Grant Approval | Maximum Time To Grant Approval | Rating & Feedback |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Tree Cutting Permission | 30 |
Sr. No. | Name of Service | Average Fee |
Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act |
Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval | Minimum Time To Grant Approval | Maximum Time To Grant Approval |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Retail Drug License (Pharmacy) (Registration and Renewal) | - | 30 Days | 55 | 55 | 55 | 0 | 29 | 28 | - | - |
2 | Wholesale Drug License (Registration and Renewal) | - | 30 Days | 24 | 24 | 20 | 4 | 27 | 29 | - | - |
3 | Drug Manufacturing License (registration and Renewal) | - | 45 Days | 18 | 18 | 18 | 0 | 41 | 43 | - | - |